You are a senior estimator of a construction company. You have collected and finalized subcontractors to carry with your tender. You need to finalise your
You are a senior estimator of a construction company. You have collected and finalized subcontractors to carry with your tender. You need to finalise your cost estimate by applying oncosts for overhead and profit. 1. Calculate your company's overheads as a percentage. Use the percentage up to two decimal places. Turnover of the company for last year: $4,132,000 Total cost of Overheads: $215,000