You are a software project manager for a software firm budgeted at 650,000$. As of today, the project should be 42% complete, but after reviewing
You are a software project manager for a software firm budgeted at 650,000$. As of today, the project should be 42% complete, but after reviewing the status of the scheduled tasks involved in the project, it is clear that only 30% of the work has been completed. The team has spent 425,000$ thus far. What is the current status of the project? 1)calculate PV, AC, EV, SPI, CPI, CV, CV%, SV, SV%, EAC, ETC. 2)write a short description of what the outcome means for the project.