You are analyzing a project network diagram and you determined that Activity R has an ES of 5, an EF of 8, a LS of
You are analyzing a project network diagram and you determined that Activity R has an ES of 5, an EF of 8, a LS of 7 and a LF 10. This means Group of answer choices Slack is 2 days Slack is between 5 and 7 days Slack is 3 days R's critical path is between 5 and 7 days long