You are at day 50 of a project. The following information shows you the data about the project plan and progress. Answer the following questions:
You are at day 50 of a project. The following information shows you the data about the project plan and progress. Answer the following questions:
====
Project Plan:
Duration: 200 Days
BAC: $400k
-------------------------
At day 50:
AC: $100k
EV: $80k
-------------------------
What are CV and SV?
What is going to be the EAC and Duration of the project if:
A: We continue with the same rates.
B: We fix the issues and return to the originally planned rates.