Question

1 Approved Answer

You are at day 50 of a project. The following information shows you the data about the project plan and progress. Answer the following questions:

You are at day 50 of a project. The following information shows you the data about the project plan and progress. Answer the following questions:

====

Project Plan:

Duration: 200 Days

BAC: $400k

-------------------------

At day 50:

AC: $100k

EV: $80k

-------------------------

What are CV and SV?

What is going to be the EAC and Duration of the project if:

A: We continue with the same rates.

B: We fix the issues and return to the originally planned rates.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Macroeconomics

Authors: David C. Colander

10th edition

1259663043, 1259663048, 978-1259663048

Students also viewed these General Management questions