You are building 5 luxury cabins over five weeks as part of a tourist development. Although each one is quite different, they each have the
You are building 5 luxury cabins over five weeks as part of a tourist development. Although each one is quite different, they each have the same budget. The budget for each cabin is for $50,000 labour and $50,000 material. Your budget uses an estimated labour rate of $100/person-hr. Your plan is to perform an equal amount of labour and material in each week, and an equal amount of labour and material for each cabin. Material is delivered just-in-time, so there is no material unused on-site at the end of each week.
Now it is the end of week #3. You have spent $124,000 on labour and $100,000 on materials. An objective calculation shows you have completed 100% of the labour and material on cabins 1 and 2, 80% on cabin 3, and have made no progress on cabins 4 and 5.
Assuming the rate of progress continues, and with no further information available, what is your most accurate calculation of the eventual final cost?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started