You are building a product A A is made up of 2 units of B and 3 units of C. C is made of 3
You are building a product A A is made up of 2 units of B and 3 units of C. C is made of 3 units of B What is the low level code for each part. Given the following information: Part Inventory Scheduled Receipts 10 (period 2) 30 (period 3) 3 2 periods 20 (period 2) Multiples of 100 The master schedule for W shows 40 parts in period 8, 50 parts in period 9,60 parts in period 10. Lead-time 1 Lot Size Lot for Lot A B 20 40 70 2