Question
1 Approved Answer
You are choosing between two projects. The cash flows for the projects are given in the following table ($ million): Year 0 - $52
You are choosing between two projects. The cash flows for the projects are given in the following table ($ million): Year 0 - $52 Project A B - $102 a. What are the IRRS of the two projects? Year 1 $26 $19 Year 2 $20 $41 Year 3 $22 $49 b. If your discount rate is 4.8%, what are the NPVs of the two projects? c. Why do IRR and NPV rank the two projects differently? Year 4 $16 $60
Step by Step Solution