You are considering a project which has been assigned a discount rate of 5 percent. If you start the project today, you will incur an
You are considering a project which has been assigned a discount rate of 5 percent. If you start the project today, you will incur an initial cost of $3,700 and will receive cash inflows of $2,500 a year for 2 years. If you wait one year to start the project, the initial cost will rise to $3,920 and the cash flows will increase to $2,857 a year for 2 years. What is the value of the option to wait? (Do not round intermediate calculations.) $488.98 $2,718.37 $605.85 O $443.81 $377.51
Step by Step Solution
There are 3 Steps involved in it
Step: 1