Question
You are considering the following two projects and can only take one. Your cost of capital is 10.9%. The cash flows for the two projects
You are considering the following two projects and can only take one. Your cost of capital is
10.9%. The cash flows for the two projects are as follows ($ million):
Project | Year 0 | Year 1 | Year 2 | Year 3 | Year 4 |
A | $102 | $26 | $30 | $38 | $48 |
B | $102 | $48 | $38 | $30 | $18 |
a. What is the IRR of each project?
b. What is the NPV of each project at your cost of capital?
c. At what cost of capital are you indifferent between the two projects?
d. What should you do?
a. The IRR for project A is
()%.
(Round to one decimal place.)
The IRR for project B is
()%.
(Round to one decimal place.)
b. The NPV for project A is
$()
million.(Round to two decimal places.)
The NPV for project B is
$()
million.(Round to two decimal places.)
c. You will be indifferent if the cost of capital is
()%.
(Round to one decimal place.)
d. Given your cost of capital, which project would you choose?(Select the best choice below.)
A.
You should invest in project
A,
as it has the higher
NPV.
B.
You should invest in project
B,
as it has the higher
NPV.
C.
You should invest in project
A,
as it has the higher
IRR.
D.
You should invest in project
B,
as it has the higher
IRR.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started