You are considering two independent projects that have differing requirements. Project A has a required return of 12 percent compared to Project B's required return
You are considering two independent projects that have differing requirements. Project A has a required return of 12 percent compared to Project B's required return of 13.5 percent. Project A costs $75,000 and has cash flows of $21,000, $49,000, and $12,000 for Years 1 to 3, respectively. Project B has an initial cost of $70,000 and cash flows of $15,000, $18,000, and $41,000 for Years 1 to 3, respectively. Based on the NPV, you should: