Question
You are considering two independent projects with the following cash flows. The required return for both projects is 10%. Given this information, which one of
You are considering two independent projects with the following cash flows. The required return for both projects is 10%. Given this information, which one of the following statements is correct?
Year Project A Project B
0 -$950,000 -$125,000
1 $330,000 $55,000
2 $400,000 $50,000
3 $450,000 $50,000
A.You should accept project B since it has the higher IRR and reject project A because you can not accept both projects.
B.You should accept project A because it has the lower NPV and reject project B
c.. You should accept project A because it has the higher NPV and you can not accept both projects.
d.You should accept project B because it has the higher IRR and reject project A.
e.You should accept both projects if the funds are available to do so since both NPV's are > 0.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started