You are creating a customer database for the Modesto Nuts minor league baseball team. Draw a project network given the information below. Complete the forward

You are creating a customer database for the Modesto Nuts minor league baseball team. Draw a project network given the information below. Complete the forward and backward pass, compute activity slack, and identify the critical path. How long will this project take? How sensitive is the network schedule? Calculate the free slack and total slack for all noncritical activities.

Provide the Early Start, Early Finish, Late Start, and Late Finish times for each activity. Compute the Total Slack for each activity. Determine which activities are on the critical path. How long will it take to complete the project?

An activity that is on the critical path for this project has increased by 7. Will the project end date be delayed? If so, by how much?

ID Description Predecessor (days) A Systems design None 2 B Subsystem A design A 1 C Subsystem B design A 1 D Subsystem C design A 1 E Program A B 2 F Program B C 2 G Program C D 2 H Subsystem A test E 1 I Subsystem B test F 1 J Subsystem C test G 1 K Integration H, I, J 2 L Integration test K 1

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Auditing Beyond Compliance Using The Portable Universal Quality Lean Audit Model

Authors: Janet Bautista Smith

1st Edition

0873898400, 9780873898409

More Books

Students also viewed these Accounting questions