Question

1 Approved Answer

You are developing a budget for a project at your contracting firm that includes: -34 hours of an Architect I ($130/hr) -6 hours of an

You are developing a budget for a project at your contracting firm that includes:

-34 hours of an Architect I ($130/hr)

-6 hours of an Architect III ($155/hr)

-42 hours of an Engineer III ($155/hr)

-20 hours of an Engineer I ($130/hr)

-6 hours of a Professional Surveyor I ($130/hr)

-4 hours of a Planner 1 ($80/hr)

-$32,337 in supplies and equipment costs

-$6,341 in travel costs

Give a detailed budget showing Direct Costs, Benefits (assume a 32% rate for Benefits), Overhead (assume 127%), and Profit (assume 12%).

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Fundamental Principles Of Finance

Authors: Robert Irons

1st Edition

1138477524, 9781138477520

More Books

Students also viewed these Accounting questions

Question

Let (x) = -3x + 4 and g(x) = -x 2 + 4x + 1. Find the following. g()

Answered: 1 week ago

Question

=+9. Think about a campaign direction.

Answered: 1 week ago

Question

=+Who is the audience?

Answered: 1 week ago