You are developing a performance progress report for a project you are managing. The following time - phased budget was developed earlier in the planning

You are developing a performance progress report for a project you are managing. The following time-phased budget was developed earlier in the planning stage and is being used as the standard against which the project performance is measured.
Work Packages W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11
A 172
B 723
C 39122
Total 17272339122
You are analyzing the project performance at the end of Week 5. Activity "B" is 40% complete and its actual cost is 15. What is the Schedule Performance Index of this activity?
Use two decimal places in your calculations.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Stage Management

Authors: Lawrence Stern, Jill Gold

12th Edition

0367647893, 978-0367647896

More Books

Students also viewed these General Management questions

Question

5.2 Summarize the environment of recruitment.

Answered: 1 week ago