You are expected to answer the following four questions referring to Table 1 and Table 2 . Table 1 shows the product backlog for a
You are expected to answer the following four questions referring to Table and Table Table
shows the product backlog for a software development project. The corresponding MoSCoW
prioritisation and effort estimate in Story Points for each user story are also shown in Table
Table shows the corresponding initial Iteration Schedule.
Table : Product Backlog
Table : Iteration Schedule
a If the iteration length is weeks and each developer is expected to work ideal days per
week, then how many developers will be needed to complete this software development
project?
b During iteration it turns out that user stories A and E take ideal days in total to complete.
Calculate the iteration hit rate for iteration
c During the sprint planning meeting for iteration it turns out that B is an epic that should
be divided into two user stories B and B to be completed within iteration in and
ideal days, respectively. What will be the updated version of the iteration schedule?
Calculate the iteration hit rate for iteration
d During iteration B and B gets completed, but turns out to be an epic to be split into
user stories J and J that will take and SPs to complete. Which other user stories will
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started