You are expected to answer the following four questions referring to Table 1 and Table 2 . Table 1 shows the product backlog for a
You are expected to answer the following four questions referring to Table and Table Table shows the product backlog for a software development project. The corresponding MoSCoW prioritisation and effort estimate in Story Points for each user story are also shown in Table Table shows the corresponding initial Iteration Schedule. Table : Product Backlog Table : Iteration Schedule a If the iteration length is weeks and each developer is expected to work ideal days per week, then how many developers will be needed to complete this software development project? b During iteration it turns out that user stories A and E take ideal days in total to complete. Calculate the iteration hit rate for iteration c During the sprint planning meeting for iteration it turns out that B is an epic that should be divided into two user stories B and B to be completed within iteration in and ideal days, respectively. What will be the updated version of the iteration schedule? Calculate the iteration hit rate for iteration d During iteration B and B gets completed, but turns out to be an epic to be split into user stories J and J that will take and SPs to complete. Which other user stories will
You are expected to answer the following four questions referring to Table and Table Table
shows the product backlog for a software development project. The corresponding MoSCoW
prioritisation and effort estimate in Story Points for each user story are also shown in Table
Table shows the corresponding initial Iteration Schedule.
Table : Product Backlog
Table : Iteration Schedule
a If the iteration length is weeks and each developer is expected to work ideal days per
week, then how many developers will be needed to complete this software development
project?
b During iteration it turns out that user stories A and E take ideal days in total to complete.
Calculate the iteration hit rate for iteration
c During the sprint planning meeting for iteration it turns out that B is an epic that should
be divided into two user stories B and B to be completed within iteration in and
ideal days, respectively. What will be the updated version of the iteration schedule?
Calculate the iteration hit rate for iteration
d During iteration B and B gets completed, but turns out to be an epic to be split into
user stories J and J that will take and SPs to complete. Which other user stories will
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started