You are given the following data regarding the Earned Value results of a project. There are no
Fantastic news! We've Found the answer you've been seeking!
Question:
You are given the following data regarding the Earned Value results of a project. There are no approved change orders for this project.Calculate ETC, EAC and VAC.
Budget | $4.600,000 |
Duration | 600 days |
Status | 80 days |
EV | $540,000 |
PV | $580,000 |
AC | $980,000 |
BAC | ? |
Assume that the same spend rate continues
1)ETC =
2)EAC =
3)VAC =