Question
1 Approved Answer
You are given the following data regarding the Earned Value results of a project. There are no approved change orders for this project.Calculate ETC, EAC
You are given the following data regarding the Earned Value results of a project. There are no approved change orders for this project.Calculate ETC, EAC and VAC.
Budget | $500,000 |
Duration | 900 days |
Status | 600 days |
EV | $180,000 |
PV | $150,000 |
AC | $178,000 |
BAC | ? |
Assume that future cost estimates are accurate and do not change.
1)ETC =
2)EAC =
3)VAC =
Step by Step Solution
There are 3 Steps involved in it
Step: 1