You are having a discussion with the key stakeholder about the best estimating method to use for the upcoming project. You argue for what provides

You are having a discussion with the key stakeholder about the best estimating method to use for the upcoming project. You argue for what provides the best team buy-in, while your stakeholder argues for a bottom-up estimate. What is the real issue?

A There is no issue - you are both talking about the same thing You are correct and the stakeholder is just not getting it.

B The stakeholder is correct and you're just not getting it

C You are correct and the stakeholder is just not getting it.

D You are both incorrect and need to explore other options.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

MIS Essentials

Authors: David M Kroenke

1st Edition

0136075606, 9780136075608

More Books

Students also viewed these General Management questions

Question

=+ (b) Show that each h, is stable-see Problem 28.10.

Answered: 1 week ago

Question

6. How can hidden knowledge guide our actions?

Answered: 1 week ago