You are in charge of planning and coordinating next falls sales management training program for your company. You have never done this before, but you
- You are in charge of planning and coordinating next falls sales management training program for your company. You have never done this before, but you decided to use the lessons from your class to develop a table of tasks to be done, their immediate predecessors, and the most pessimistic, optimistic, and frequent times for each task. The table you developed is below:
Task | Immediate Predecessor | Task completion time estimate (weeks) | Mean | Variance | ||
Optimistic | Most probable | Pessimistic | ||||
A | -- | 1.5 | 2 | 2.5 | 2 | 0.02778 |
B | A | 2 | 2.5 | 6 | 3 | 0.44444 |
C | -- | 1 | 2 | 3 | 2 | 0.11111 |
D | C | 1.5 | 2 | 2.5 | 2 | 0.02778 |
E | B,D | 0.5 | 1 | 1.5 | 1 | 0.02778 |
F | E | 1 | 2 | 3 | 2 | 0.11111 |
G | B,D | 3 | 3.5 | 7 | 4 | 0.44444 |
H | G | 3 | 4 | 5 | 4 | 0.11111 |
I | F,H | 1.5 | 2 | 2.5 | 2 | 0.02778 |
- On the next page, draw the CPM/PERT diagram, filling in the values for the task times, earliest and latest start and finish.
- What is the expected project completion time?
- What is the critical path?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started