You are leading a project that includes risk to either permanently damage or significantly improve the reputation of the organization with its customer base. You
You are leading a project that includes risk to either permanently damage or significantly improve the reputation of the organization with its customer base. You decide to call a meeting with the organization's management to make them aware of the issue and discuss possible options. Which risk response strategy are you applying? Group of answer choices Passive acceptance Escalate Active acceptance Transfer