You are managing a construction project that was scheduled to be completed in 1 2 months with a budget at completion ( BAC ) of

You are managing a construction project that was scheduled to be completed in 12 months with a budget at completion (BAC) of $600,000. At the end of month 6, your team has finished 40% of the project work, spending $270,000. However, according to the schedule, you should have completed 50% of the project by this time.
Using Earned Value Management (EVM), determine the project's cost and schedule performance and identify the best course of action.
The project is over budget and behind schedule; perform a root cause analysis and consider corrective actions.
The project is under budget and behind schedule; request additional funds and accelerate activities.
The project is under budget and ahead of schedule, so continue as planned.
The project is over budget and ahead of schedule; reduce costs and continue with the planned schedule.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Understanding Management

Authors: Richard L Daft, Dorothy Marcic

6th Edition

9780324581782, 324581785, 978-0324568387

More Books

Students also viewed these General Management questions

Question

The most common and troublesome project issue is called

Answered: 1 week ago