Question

1 Approved Answer

You are managing a project and are looking at project performance. At this time, the earned value is $145, planned value is $162 and the

You are managing a project and are looking at project performance. At this time, the earned value is $145, planned value is $162 and the actual cost is $138. The project has an approved budget of $200. What is the required cost efficiency needed to finish the project on budget?

a. 0.895

b. 1.051

c. 0.887

d. not enough information to calculate

e. none of the above

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Casebook On General Management In Asia Pacific

Authors: Dominique Turpin, Xiaobai Shen

1st Edition

0333717910, 978-0333717912

More Books

Students also viewed these General Management questions

Question

Moving averages are

Answered: 1 week ago