You are managing a project and have developed your schedule network diagram and have identified two paths. Path 1, has two activities of a duration
You are managing a project and have developed your schedule network diagram and have identified two paths. Path 1, has two activities of a duration of 2 and 5 days respectively. Path 2 has three activities with durations of 1, 3 and 3 days respectively. Which of the two paths is called critical path? A. Path 1 O B. Path 2 C. Both path 1 and path 2 O D. Neither