You are managing a project with a BAC of $8,000. You had planned to have 60% of the work done by now, but you have
You are managing a project with a BAC of $8,000. You had planned to have 60% of the work done by now, but you have finished 70% of the work. What is the Planned Value? which percentage should be used to calculate planned value