You are managing an agile project and measure small amounts of variance in task duration. You should: Group of answer choices Undertake root-cause analysis to
You are managing an agile project and measure small amounts of variance in task duration. You should: Group of answer choices Undertake root-cause analysis to eliminate it Diagnose the issue as part of your Scrum Master role Accept some variance an inevitable Engage the team in diagnosing the