Question
You are managing an eight-month project with a BAC of $100K. On Friday afternoon, at the end of the fourth month (half way through the
You are managing an eight-month project with a BAC of $100K. On Friday afternoon, at the end of the fourth month (half way through the project), your EVM system provides the following values:
BCWS=$50K BCWP = $55k ACWP = $75k Your boss asks you to present the EAC at the Monday morning status meeting. You have been an attentive project manager and you have been especially pleased that the BCWP has been tracking quite well to the BCWS. Below are listed three possible answers one might provide as the EAC.
For each possible answer, first list any assumptions necessary and then provide the rationale and analysis, which would justify or explain it.
$100k:
$125k:
$150k:
Having done the analysis and considered the explanations for each of these answers, which answer would you be most comfortable presenting to your boss? Why?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started