You are now in week 10. After the analysis done in week 8, the new data collected now find that the progress of 'build' is
You are now in week 10. After the analysis done in week 8, the new data collected now find that the progress of 'build' is 65% in week 9 and increase to 75% in week 10. The next phase of installation has not started. The project spent another RM5000 at week 9 and RM6000 at week 10 for the 'build' phase. Now calculate the new earned value in week 10. Using CPI and CV, compare performance at week 10 with week 8. Calculate the new FCAC and TCPI. Explain.