Answered step by step
Verified Expert Solution
Question
1 Approved Answer
You are now in week 10. After the analysis done in week 8, the new data collected now find that the progress of build is
You are now in week 10. After the analysis done in week 8, the new data collected now find that the progress of build is 65% in week 9 and increase to 75% in week 10. The next phase of installation has not started. The project spent another RM5000 at week 9 and RM6000 at week 10 for the build phase. Now calculate the new earned value in week 10. Using CPI and CV, compare performance at week 10 with week 8. Calculate the new FCAC and TCPI. Explain.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started