Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

You are one of five carpenters assigned to complete a short construction project. Right before the start of the project, one of your fellow carpenters

You are one of five carpenters assigned to complete a short construction project. Right before the start of the project, one of your fellow carpenters is hospitalized and will not be available to work on the project. Develop a resource-constrained schedule to see how long the project will take with only 4 carpenters. Be sure to record the order in which you schedule the activities using the scheduling heuristics. The number of carpenters required for each activity is as shown in the diagram. No splitting of activities is possible. You will receive a bonus if the project is completed within 19 days.Note: Recall, in the schedule resource load chart the time-constrained scheduling interval (ES through LF) has
been shaded. Any resource scheduled beyond the shaded area will delay the project. "TP" stands for time period.
List the order in which you scheduled the activities of the project
Which activities are now critical?
Critical activities are
Recompute your slack for each activity given your new schedule. What is the slack for:
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Small Business Management Entrepreneurship and Beyond

Authors: Timothy s. Hatten

5th edition

538453141, 978-0538453141

More Books

Students also viewed these General Management questions