You are performing an earned value analysis on your 25-week project. The project was scheduled to be 60 percent complete at this time. You have

You are performing an earned value analysis on your 25-week project. The project was scheduled to be 60 percent complete at this time. You have completed 16 of the 30 deliverables (all of equal value). You have spent $25,000 of your total original budget of $55,000. The first deliverable took twice as long and cost twice as much as was planned and budgeted.

Calculate the following:

  • Budget at completion
  • Actual cost
  • Planned value
  • Earned value
  • Cost variance
  • Cost performance index
  • Schedule variance

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Auditing The Art and Science of Assurance Engagements

Authors: Alvin A. Arens, Randal J. Elder, Mark S. Beasley, Joanne C. Jones

14th Canadian edition

134613112, 134835018, 9780134885254 , 978-0134613116

More Books

Students also viewed these Accounting questions

Question

Course Properties: Code Name Description Roster

Answered: 1 week ago

Question

Define Scientific Management

Answered: 1 week ago

Question

Explain budgetary Control

Answered: 1 week ago

Question

Solve the integral:

Answered: 1 week ago

Question

What is meant by Non-programmed decision?

Answered: 1 week ago