You are planning the work and work schedule. The preceding activity must be finished before the next activity can start. Which of the following relationships
You are planning the work and work schedule. The preceding activity must be finished before the next activity can start. Which of the following relationships best describes this? Question 47 options: Finish-to-Start Finish-to-Finish Start-to-Start Start-to-Finish