You are preparing a project to lay fiber optic cable.The first task is to mobilize the team.You estimate this will take one week and cost

You are preparing a project to lay fiber optic cable.The first task is to mobilize the team.You estimate this will take one week and cost $3000.The second task is to lay the cable.This will take three weeks and will cost $45,000.The total length of the cable is 15 miles.The last task, which will take one week, is to Terminate and test the cable.You budget $5000 for this.At the end of the first week, you have completed mobilization, but it cost a total of $4500.At the end of the third week, you have completed five miles of cable at a total cost of $28,000 (installation only).It takes you a total of 10 weeks to complete the entire project, for a total cost of $65,000.

At the end of week 1:

i.What is your SPI?

ii.What is your CPI?

iii.What is your EAC?

At the end of week 3:

i.What is your SPI?

ii.What is your CPI?

iii.What is your EAC?

At the end of the project:

i.What is your SPI?

ii.What is your CPI?

iii.What is your EAC?

Please show your work or complete in a excel file

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Personal Finance Turning Money into Wealth

Authors: Arthur J. Keown

8th edition

134730364, 978-0134730363

More Books

Students also viewed these Finance questions

Question

What medium will you use for the BCP?

Answered: 1 week ago

Question

Should your BCP be procedure-based or decision-driven?

Answered: 1 week ago