you are project manager stating a new project and many of stakeholder identified in the charter are the senior executives of the current organisation as
you are project manager stating a new project and many of stakeholder identified in the charter are the senior executives of the current organisation as is the customer. inevitability these stakeholder will not agree in everything . you should
prioritise a stakeholder
perform a probability and impact analysis
create a stakeholders register
interview stakeholder together to gain consensus of their expectation