Question

1 Approved Answer

You are responsible for managing a project with the following activities. What is the minimum crashing cost to finish the project in 18 days? Activity

You are responsible for managing a project with the following activities. What is the minimum crashing cost to finish the project in 18 days?

ActivityPredecessorNormal Time (days)Maximum Crash Time (days)Crashing Cost/day
A--51$200
B--71$500
C--51$200
DA102$300
EB61$400
FA, C72$650
GB41$500
HE, D, G61$350


Select one:

a. $1,500

b. $1,150

c. $850

d. $3,450


Step by Step Solution

3.43 Rating (162 Votes )

There are 3 Steps involved in it

Step: 1

A D E B H C F G Determine the l... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managing Operations Across the Supply Chain

Authors: Morgan Swink, Steven Melnyk, Bixby Cooper, Janet Hartley

2nd edition

9780077535063, 007802403X, 77535065, 978-0078024030

More Books

Students also viewed these Finance questions

Question

What are some guidelines for improving effectiveness as a follower?

Answered: 1 week ago

Question

Give one example of building flexibility into system capacity.

Answered: 1 week ago