Question
You are responsible for managing a project with the following activities. What is the minimum crashing cost to finish the project in 18 days? Activity
You are responsible for managing a project with the following activities. What is the minimum crashing cost to finish the project in 18 days?
Activity | Predecessor | Normal Time (days) | Maximum Crash Time (days) | Crashing Cost/day |
---|---|---|---|---|
A | -- | 5 | 1 | $200 |
B | -- | 7 | 1 | $500 |
C | -- | 5 | 1 | $200 |
D | A | 10 | 2 | $300 |
E | B | 6 | 1 | $400 |
F | A, C | 7 | 2 | $650 |
G | B | 4 | 1 | $500 |
H | E, D, G | 6 | 1 | $350 |
Select one:
a. $1,500
b. $1,150
c. $850
d. $3,450
Step by Step Solution
3.43 Rating (162 Votes )
There are 3 Steps involved in it
Step: 1
A D E B H C F G Determine the l...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get StartedRecommended Textbook for
Managing Operations Across the Supply Chain
Authors: Morgan Swink, Steven Melnyk, Bixby Cooper, Janet Hartley
2nd edition
9780077535063, 007802403X, 77535065, 978-0078024030
Students also viewed these Finance questions
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
View Answer in SolutionInn App