You are responsible for managing an advertising project with the following activities ( times are given in weeks ) . Immediate Normal Time Crash Time
You are responsible for managing an advertising project with the following activities times are given in weeks
Immediate
Normal Time
Crash Time
Normal
Crash
Activity
Predecessor
Weeks
Weeks
Cost $
Cost $
A
none
$
$
B
none
$
$
C
none
$
$
D
A B
$
$
E
C
$
$
F
A
$
$
G
D E F
$
$
What is the critical path for this project?
Group of answer choices
AFG
ADG
BDG
CEG