You are suppose to bid for building 50 units of a special-purpose robot. It is expected that the first robot will take 120 hours to

You are suppose to bid for building 50 units of a special-purpose robot. It is expected that the first robot will take 120 hours to build. Historically, your company team's learning rate is 90% (i.e. assembly time is reduced by 10% every time the output is doubled). If the per hour manpower rate for the team is RM 100, what should be the minimum amount you should bid to avoid loosing money.

To expedite, you may average the time required for the first and the last unit to compute the total time required.

Please note that the cost of facilities and materials are to be provided by the company asking for the bid. Select the closest matching answer.

a.

465,528

b.

750,347

c.

5,32,454

d.

662,115

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Advanced Financial Accounting Lawrence S C Good Condition ISBN 08512

Authors: S.C. Lawrence

1st Edition

9780851215099

More Books

Students also viewed these Accounting questions