You are the general contractor for a new mid-rise office building. Due to an issue with monitoring painting, the interiors have completed but you are
You are the general contractor for a new mid-rise office building. Due to an issue with monitoring painting, the interiors have completed but you are behind schedule and still need to complete testing for the mechanical, electrical, and plumbing systems. Explain what order you conduct your testing and why? (Assume each system takes one full day to test and problem solve; and you have three days remaining in the schedule)