Question
You are the IT project manager of U Design Inc. The company is initializing a new software project. You, as the IT project manager, need
You are the IT project manager of U Design Inc. The company is initializing a new software project. You, as the IT project manager, need to make plans for the project, starting with making a schedule based on the given information in the table.
Activity | Immediate Predecessors | Completion Time (months) |
---|---|---|
A | -- | 3 |
B | A | 3 |
C | CA | 2 |
D | DB | 3 |
E | C | 7 |
F | B,C | 3 |
G | D,E | 6 |
H | C | 2 |
The company wants to know:
1. What is the total time to complete the software project?
2. Which activities are critical to the timely completion of the project?
3. What are the earliest start/finish and latest start/finish times for each activity?
4. What will happen if activity C is delayed by 2 months?
5. What will happen if activity B is delayed by 5 months?
6. If you can use extra resources to crash the project, which activities you should consider first?
7. Use the CPM to draw a network diagram to show the critical path for this project. You can upload a screenshot or a picture of your CPM network.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started