Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

You are the manager if an IT project to develop and install a customer relationship management (CRM) module within your company's enterprise IT system. So

image text in transcribed
image text in transcribed
You are the manager if an IT project to develop and install a customer relationship management (CRM) module within your company's enterprise IT system. So far, you have planned only the first phase of the project, which doesn't include the soft launch (to test the system live), user input, corrections, or final launch. A network diagram showing the first phase of project schedule appears below. Costs are spread evenly over the activity times. continues in this way. The project plan gets revised and you now have a new baseline budget given to you (Tab: Revised Budget) go to this worksheet and complete all the entries the EVM tables given for each update. Then, at the end period 8, give an assessment on project's progress in terms of its budget and schedule, if the project progress Project: CRM Budget Assess User Requirements $20,000 $5,000 $5,000 $5,000 8 $5,000 9 11 Assess Current System 12 13 14 $30,000 15 $10,000 16 $10,000 Specify System Requirements $10,000 17 18 19 20 21 $30,000 Send RFP for Software Vendors $15,000 $15,000 $15,000 Send RFP for Hardware Vendors $15,000 $5,000 $5,000 $5,000 Select Software Vendor $7,000 $10,000 $5,000 Select Hardware Vendor $8,000 $7,000 Program and Test the Module $200,000 $8,000 Train Users $100,000 Cumulative $25,000 $25,000 $25,000 $25,000 $25,000 $25,000 $25,000 $25,000 $25,000 $25,000 $25,000 $25,000 Week 4 BAC Activity % Complete AC EV Assess User Requirements PV TSV Planned Duration 100% $20,000 Tov SPI CPI Assess Current System 100% $32,000 Forecast for cost (EAC$)? Cumulative Forecast for completion time (ETC Time) TCPI What is your overall assessment at this period (Week 8) , does it appear Week 8 that the project is likely to finish on-time and on-budget? Why or why Activity % Complete TAC EV Assess User Requirements PV TSV TCV not? Explain your assessment (your response should not exceed the 100% $25,000 SPI TCPI Forecast for cost (EAC$)? space provided here). Assess Current System 100% $32,000 Forecast for completion time (ETC Time)? Specify System Requirement 100% $18,000 TCPI Send RFP for Software Vendors 100% $8,000 Send RFP for Hardware Vendors 50% Cumulative $10,000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Essentials Of Strategic Management

Authors: J. Hunger, Thomas Wheelen

5th Edition

0136006698, 9788120348615

More Books

Students also viewed these General Management questions

Question

Do not get married, wait until I come, etc.

Answered: 1 week ago

Question

Do not come to the conclusion too quickly

Answered: 1 week ago

Question

Engage everyone in the dialogue

Answered: 1 week ago