Question
You are the newly appointed senior project manager for ABX Corporation, a private company who are proud sponsors of the new Cape Town to Durban
You are the newly appointed senior project manager for ABX Corporation, a private company
who are proud sponsors of the new Cape Town to Durban high-speed train project. The project
will incorporate the latest technology in design, construction and delivery of a high-speed train
between Cape Town Station and Durban Station.
You and your project team hold a risk identification and allocation meeting. During the meeting
the team discusses the following:
Cape Town Station:
1. Currently there are 85 operational train sets, made up of 1 094 coaches.
2. There are 671 scheduled trains per weekday, operating over 460 kilometres of track
to 122 stations and 4 halts.
3. In 2018 there were around 500 000 daily users of the service. The services are
divided into three areas, each of which has various branches.
Durban Station:
1. Currently there are 35 000 daily users of the service.
2. There are 125 scheduled trains per weekday.
3. The station was revamped recently and is now world-class. The management of the
station has indicated that they would not consider allowing any private trains to use
their facility.
The Rail Route:
1. The route runs through rural areas where farm stock roam freely.
2. The technology requires the train tracks to be as flat as possible. Tunnels and bridges
will therefore have to be constructed, or alternatives should be considered.
3. All structures to be built for the rail infrastructure will require an environmental
assessment, which could take up to three years to complete.
4. The train will use a large amount of electricity, which means that the pressure on the
South African electrical infrastructure will increase drastically.
5. Security companies will be employed to ensure that the material is guarded during
construction.
1.1 Identify at least five risks associated with the project and give a risk rating for each by
using a 4 x 4 matrix as in Figure 1. (25)
Risk example: Getting material to the construction sites in the rural areas
1.2 Management asks you to propose possible responses to these risks. (5)
You are the newly appointed senior project manager for ABX Corporation, a private company
who are proud sponsors of the new Cape Town to Durban high-speed train project. The project
will incorporate the latest technology in design, construction and delivery of a high-speed train
between Cape Town Station and Durban Station.
You and your project team hold a risk identification and allocation meeting. During the meeting
the team discusses the following:
Cape Town Station:
1. Currently there are 85 operational train sets, made up of 1 094 coaches.
2. There are 671 scheduled trains per weekday, operating over 460 kilometres of track
to 122 stations and 4 halts.
3. In 2018 there were around 500 000 daily users of the service. The services are
divided into three areas, each of which has various branches.
Durban Station:
1. Currently there are 35 000 daily users of the service.
2. There are 125 scheduled trains per weekday.
3. The station was revamped recently and is now world-class. The management of the
station has indicated that they would not consider allowing any private trains to use
their facility.
The Rail Route:
1. The route runs through rural areas where farm stock roam freely.
2. The technology requires the train tracks to be as flat as possible. Tunnels and bridges
will therefore have to be constructed, or alternatives should be considered.
3. All structures to be built for the rail infrastructure will require an environmental
assessment, which could take up to three years to complete.
4. The train will use a large amount of electricity, which means that the pressure on the
South African electrical infrastructure will increase drastically.
5. Security companies will be employed to ensure that the material is guarded during
construction.
1.1 Identify at least five risks associated with the project and give a risk rating for each by
using a 4 x 4 matrix as in Figure 1. (25)
Risk example: Getting material to the construction sites in the rural areas
1.2 Management asks you to propose possible responses to these risks. (5)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started