Question: You are the project lead of a large application development project to implement an e - commerce portal for your client. You are now at

You are the project lead of a large application development project to implement an e-commerce portal for your client. You are now at the end of system testing and would like to understand how robust the initial requirements phase of the project was. Which of the following would be the best metric for this?
Select one:
a. Number of change requests post requirements phase
b. None of the other answers is correct
c. Number of defects by origin phase
d. Number of initial requirements (end of requirements phase)/total number of requirements currently
 You are the project lead of a large application development project

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!