Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

You are the project manager for a team of 7 developers, and you have decided to use XP because of the small size of the

You are the project manager for a team of 7 developers, and you have decided to use XP because of the small size of the team and the type of the project. At the end of iteration 1, the following information has been collected for the total work done by each developer (Note: not every developer is full-time, as observed from the information below)

Original estimate 4 days 8 days 5 days 4 days 9 days 10 days 7 days Actual time needed 5 days 10 days 10 days 8 days 9 days 6 

If 2-calendar-week iterations are used here, what is the project velocity? Assume there were no official holidays in iteration 1

You want to schedule iteration 2 from the work repository below. Using the project velocity from iteration 1, and assuming 1 long weekend (3-day weekend) in the next 2 weeks, which tasks will make it to iteration 2? Ignore actual assignment of the tasks to specific develop

Original estimate 4 days 8 ays 5 days 4 days 9 days 10 days 7 days Actual time needed 5 days 10 days 10 days 8 days 9 days 6 days 8 days

Step by Step Solution

3.45 Rating (152 Votes )

There are 3 Steps involved in it

Step: 1

If 2calendarweek iterations are used here what is the project velocity Assume there were no official ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Transport Operations

Authors: Allen Stuart

2nd Edition

978-0470115398, 0470115394

More Books

Students also viewed these General Management questions