You are the project manager for the BKL Project. This type of project has never been attempted before by your organization. The stakeholders already have
You are the project manager for the BKL Project. This type of project has never been attempted before by your organization. The stakeholders already have high requirements for the project deliverables and you need to create a change control system. This system should be controlled by which of the following? a. The Change Control Board b. It is specific to the organizational structure c. A formal change control form d. It should be completed by the team