Question
You are the project manager for three different projects. Project A: This project is scheduled to take 35 weeks to complete. You are in the
You are the project manager for three different projects.
Project A: This project is scheduled to take 35 weeks to complete. You are in the planning stage of the project. You need to reduce the schedule for this project by 7 weeks. This project has a number of predecessors that were created by the project teams preference. The sponsor insists on having all the work done on time without unduly increasing risk or costs to the project.
Project B: This project is in the execution stage of the project. It is behind schedule by 5 weeks; it was scheduled to be completed in 10 weeks. The sponsor is desperate to accomplish something on this project. The budget is limited to the original amount, and all soft predecessors have already been removed.
Project C: This project is behind schedule by 10 weeks. It was to have been completed in 2 months. The sponsor has additional funds to help complete the project on time if needed but does not want to increase risk to the project.
For each of the projects above, choose an appropriate schedule compression technique. Explain your choice.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started