You are the project manager of a project to create the e-commerce platform for your company, and you are evaluating the project performance measured against
You are the project manager of a project to create the e-commerce platform for your company, and you are evaluating the project performance measured against the project baseline on a regular basis. In doing so, you are performing processes that belong to which of the following process groups? Question 5 options: Planning Executing Monitoring and controlling Evaluating