You are the project manager of an e - business application development project in your company. Your Lead Analyst and Junior Programmer have informed you
You are the project manager of an ebusiness application development project in your company. Your Lead Analyst and Junior Programmer have informed you that your project will benefit from using Function Points and COCOMO methods for estimating software cost and effort. Current project is comprised of three modules. The following pieces of information are available:
Note: SLOC is Source Lines of Code.
Table : Size and Function Point estimates
Module
Module Size Estimated SLOC or Function Points
Module
SLOC
Module
SLOC
Module
Visual C# language will be used to implement the following function points:
Inputs: average, high
Outputs: average, high
User Inquiries: simple, average, high
Interfaces: simple, average, high
Files: simple, average, high
Based on the prior experiences, function point parameters are according to the table
Table : FPA Weight Parameters
Parameter
Simple
Average
High
Inputs
Outputs
User Inquiries
Interfaces
Files
The Value Adjustment Factor VAF for this project is
A function point is approximately lines of Visual C# code. In other words, the AVC for C# programming language is
Task : Estimate the SLOC for module using FPA.
You can find the total Source Lines of Code for the project by adding SLOC for the three modules.
Based on the analysis that has been performed so far, the project has been labeled as a complex embedded project.
The organization you work for has an average labor rate including all benefits of $month for its developers.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started