You are the project manager of the JHD Project. Your project will cost your organization $ 2 5 0 , 0 0 0 to complete

You are the project manager of the JHD Project. Your project will cost your organization $250,000 to complete over the next eight months. Once the project is completed, the deliverables will begin earning the company $3500 per month. What will be the payback period for this project?