Answered step by step
Verified Expert Solution
Question
1 Approved Answer
You are the project manager of the software installation project in the table below. You would like to find the minimum - cost schedule for
You are the project manager of the software installation project in the table below. You would like to find the minimum cost schedule for your project. There is a $ per week penalty for each week the project is delayed beyond week ?In addition, your project team determined that indirect project costs are $ ?per week.
Activity Immediate Predecessor s ?Normal Time weeks ?Normal Cost $ ?Crash Time weeks ?Crash Cost $
A
B
C A
D A ?B
E B
F D
G E ?F
H G
I C ?F
a ?What would be your target completion week?
The target completion week is week
enter your response here. Enter your response as an integer.
Part
b ?How much would you save in total project costs with your schedule?
Total Savings$
enter your response here. Enter your response as an integer.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started