You are three months into a six month project. Assume the budget burn rate is constant. The budget at completion (BAC) is $120,000. AC =
You are three months into a six month project. Assume the budget burn rate is constant. The budget at completion (BAC) is $120,000. AC = $65,000. The SPI = 1.2. What is the CPI of this project? (Round