Answered step by step
Verified Expert Solution
Question
1 Approved Answer
You are using a triangular PERT formula to estimate an activity's duration. What information do you need to complete this estimate? a the activity's early
You are using a triangular PERT formula to estimate an activity's duration. What information do you need to complete this estimate? a the activity's early start date and early finish date b the optimistic, most likely, and pessimistic values for the activity c the activity's late start date and late finish date d the activity's predecessor and successor activities e Leave blank for now. I'll submit my answer later
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started